Construction phase plan template. A printable construction phase plan pro-forma covering the project, the arrangements for managing it, and the significant risks and how they are controlled.
This is the structure of a plan, not a plan. Whether yours is suitable and proportionate for your project is a judgement for somebody competent in construction health and safety, and neither this sheet nor BuildOptix makes it for you — what the platform does is keep the plan, the RAMS and the site records together and current rather than in three folders.

What is on the sheet
- Project details, the client, the duty holders under CDM and who is appointed to what
- Description of the work, the programme and the site itself
- Management arrangements: who is in charge, how people are inducted, how changes are handled
- Site rules, welfare, emergency arrangements and first aid
- Significant risks arising from the work, and the controls for each — not a generic hazard list
- A review block, because the plan is supposed to change as the job does
Why this record matters
CDM 2015 requires a construction phase plan for every project, and the plan has to be proportionate to the work. That second half is where most plans go wrong in both directions: a loft conversion with a ninety-page plan nobody reads, or a complex refurbishment with a four-page one that names no significant risks at all.
The section that distinguishes a real plan from a template with a logo on it is the significant risks. A generic list of construction hazards tells an inspector nothing and tells the people on site less. What belongs there is what is actually dangerous about this job — the live services, the fragile roof, the deep excavation, the asbestos survey nobody has done yet — and what is being done about each one.
The review block exists because a construction phase plan is a living document and is almost universally treated as a one-off. The job changes, the sequence changes, a new trade arrives with a risk nobody planned for, and the plan in the folder still describes the job as it was tendered.
This is tiered as a soft download and honestly so. Producing a suitable plan for anything beyond a simple project is work for somebody competent, and a pro-forma is a structure to work within rather than a substitute for that.
Use it with
- RAMS templateA printable risk assessment and method statement — the hazards and controls on one side, the sequence of work on the other, and the briefing record that proves the gang was told.
- Subcontractor competence checklistA printable checklist for assessing a subcontractor before they start — organisational capability, insurance, RAMS, the people they are sending and the evidence behind each.
- Site inspection recordA printable site safety inspection record — a structured walk of the site, what was found, who owns each finding and whether it was closed.
Read more on this
© 2026 BuildOptix. Free to print, copy and use in your business. Not for resale. Please keep this notice.
Contains public sector information licensed under the Open Government Licence v3.0. General guidance, not legal advice. Checked October 2026.