What is an F10 notification?

An F10 is the notification a client gives the Health and Safety Executive for a construction project that exceeds the notification thresholds in CDM 2015, submitted before the construction phase begins.

F10 notification — diagram An F10 is the notification a client gives the Health and Safety Executive for a construction project that exceeds the notification thresholds in CDM 2015, submitted before the construction phase begins. Pre-construction What is already there,from the client Phase plan How this site will be run,before work starts RAMS Task by task, briefed tothe people doing it H&S file What a stranger needs toknow in fifteen years
F10 notification, shown in the documents a project produces.
Use this diagram+

Free to use on your own site, in training material or in a handout, as long as the credit link stays on it. Paste this where you want the diagram to appear.

<figure>
  <img src="https://buildoptix.co.uk/glossary/f10-notification/diagram.svg" alt="F10 notification — diagram from BuildOptix" width="880" height="620" loading="lazy">
  <figcaption>
    <a href="https://buildoptix.co.uk/glossary/f10-notification">What is an F10 notification?</a> — diagram by
    <a href="https://buildoptix.co.uk">BuildOptix</a>
  </figcaption>
</figure>

It is a client duty rather than a contractor one, which is among the most commonly misplaced responsibilities on a project. Contractors frequently submit it on the client's behalf, which is practical but does not move the duty.

Notification does not itself change the safety requirements. A notifiable project has to be run the same way a non-notifiable one does; what changes is that the regulator knows it is happening.

The notice has to be kept accurate. Projects extend and change, and a notification describing a programme that no longer exists is worth correcting rather than leaving.

What goes wrong in practice

  • Assumed to be the principal contractor's job, so on a project where nobody assumed it, it is not made.
  • Submitted after work started, which the dates record.
  • Never updated when the project extended well beyond its notified duration.
  • Treated as the compliance step, with the underlying duties considered discharged by it.